Expansion Gaps

Do you have a problem? Here is the place to appeal for help
Post Reply
JR

Expansion Gaps

Post by JR » Wed Mar 24, 2010 12:39 am

I finally about to lay down the first track this weekend but wonder how to much gap between the rails for expansion and contraction.

User avatar
Dr. Bond of the DVLR
Retired Director
Retired Director
Posts: 4516
Joined: Tue Jun 09, 2009 9:43 pm
Location: Suffolk
Contact:

Post by Dr. Bond of the DVLR » Wed Mar 24, 2010 7:23 am

I've never really taken much care over expansion gaps in this scale as I've never really been affected them. I've run in minus temperatures and the heat of summer and never had to adjust the rail. One thing I would like to do however is see if by laying bigger gaps between the rails one can get a better "clickity clack" sound!
Image
The railway which people forgot
(to build)

Merddin Emrys

Post by Merddin Emrys » Wed Mar 24, 2010 8:26 am

You could try a small cut in the top of the rail at intervals for the da dum da dum sound

METHSSNIFFER

Post by METHSSNIFFER » Wed Mar 24, 2010 9:38 am

You definatley need expansion gaps and I suggest about 1.5mm every yard of track. It is surprising how much rail does expand and if the rail is laid tightly it will lift and will need relaying.

MoelygestLR

Post by MoelygestLR » Wed Mar 24, 2010 4:14 pm

I was told the best way is to place a 1 pence peice as a jig pace it in the gap push until tight and then pop the coin out and there you go, gap set.

JR

Post by JR » Wed Mar 24, 2010 6:59 pm

Thanks. I should try the 1p idea.