New Pedestrian Rail Crossing on ASCR Part 2

Posted: Mon Nov 07, 2022 7:53 am
by GAP
I had the job of driving the diesel loco transporting the track section and the sleepers, this gave me enough logbook hours to entitle me to sit the drivers exam for my diesel driver's ticket.

Fabricated rail crossing section loaded onto train for transport to new crossing site.
The steel on the inside of the rail is for the flangeway in the concrete and will be removed later when concrete has cured
6rail for crossing.jpg
6rail for crossing.jpg (67.53 KiB) Viewed 6693 times
Rail section unloaded
7unloading crossing rail.jpg
7unloading crossing rail.jpg (76.89 KiB) Viewed 6693 times
Concrete formwork for new crossing
8new crossing formwork.jpg
8new crossing formwork.jpg (89.3 KiB) Viewed 6693 times
Positioning track section
9positioning track.jpg
9positioning track.jpg (87.78 KiB) Viewed 6693 times
Final track section alignment
10track final alignment.jpg
10track final alignment.jpg (85.49 KiB) Viewed 6693 times