Well folks, at last there has been some progress in recent days. It's only relatively minor progress but things are moving forwards! The weather has been the biggest obstacle in recent weeks. I still need to get some civil engineering out of the way before any serious railway work (track laying for instance) can get underway. I really need to get the garden side of things fit for planting, there need to be some flowers on display no later than this summer, otherwise the Charnwood Forest Light Railway will need a new Chief Engineer and I'll be looking for cheap lodgings!
Last weekends mild weather meant that it was fit to mix up some mortar and so the last bit of brickwork alongside the path went in. This also involved making a start on the footpath crossing over the line. This involved a new experience - laying a few cobbles!There is still a bit of work to do here but this will now have to wait until I extend the sides of the big troughing units up by about 3 inches. This is to enable me to use the space to store my two section ladders. I need the the lids to be at their final height before I make a permanent stopping to the 'blind' end of the construction. This is right up against the railway at the point where the path crosses and so everything is tied together at that point.
Other work this week involved mixing and pouring concrete to fill the centre of the new stone wall on top of the tunnel. I also got the two clothes line posts positioned and concreted in. Small jobs on their own but that's two more off the outstanding jobs list. Speaking of which, having reviewed said list I find there is relatively little left on it now. It came as quite a surprise after all this time!
This afternoon I was home at a sensible time, the weather was good and I thought it was a good opportunity to crack on, particularly in light of tomorrows wet forecast. I'm out of cement until I can get back to Wickes so I decided to press on with the railway foundation construction. There is precious little of that left to do either! The passing loop for the intermediate station of Woodhouse Eaves and the run-round loop of the adjacent station that will form the other terminus (but with the ability to run straight through as part of a continuous loop) are the major jobs left. There is also the question of a couple of intermediate sidings to sort but they are very minor jobs. The terminus station also needs a bit more foundation work but it's not the huge task it once was. Anyway, this afternoon I made a start on the passing loop at the intermediate station. I made good progress until both the batteries on the electric drill went flat!
It's good to be moving forwards again. Thoughts are really turning towards trackwork now! Pictures of the latest civil engineering efforts follow below.
Click to download file
This is the site of Anstey station and siding with the footpath crossing immediately beyond.
This is the footpath crossing itself. The side nearest the camera is the main area still needing to be finished.
This is the intermediate station site. Today's work is the left hand track, still very unfinished but you can see where I'm going with it!
And here is the station site looking the other way. Today's work is now on the right. To the left is the site of the terminus station that has a connection through onto the crossing loop of the intermediate station to allow continuous running.