Operation Multi Purpose
Operation Multi Purpose
Right, so as you all probably know by now I’m good at thinking of projects and starting them, but I never seem to get around to finishing them!
Many of you may have seen my post RE: Laser Cutting and the Scaling up of 7mm Drawings, (which I see also helped another member) and this finally gave me a big kick up the backside to start one of the big projects I have wanted to do for a little while, and would hopefully be a big learning curve at the same time. It wasn’t what I was originally going to do Project Wise as my original plan was to design and build a FfR Funkey to go with the rest of my stock which is slowly increasing in size, but I found this too complex having only just started out with the software coupled with it being the first stuff I'd done in CAD in years!! So I went for Option 2 which wouldn't be as complex (however I'm not saying that now after designing it though!)
The plan was to build a Multi-Purpose Vehicle which can, as its name suggests, undertake many different roles depending on the Modules fitted to it. There was also a requirement to be able to extend the unit as required and also be able to work in multiple with other units.
So after a bit of discussion with another Forum Member regarding Laser Cutting, I began to draw up a plan in LibreCAD and after a lot of frustration and swearing at the computer along with some help and advice the plan soon came together, a few obvious mistakes were ironed out it was sent off to be cut.
The parts arrived promptly within a couple of days and the Prototype was soon together, however I found a few places where I had gone wrong (solebar tabs 3mm out, cab front tabs to small etc.) but it wasn’t anything that couldn’t be changed easily ready for the Mk2 Version.
So here are a few pictures to get you started.
After a weekend of tinkering and getting everything changed and adding extra bits the plans have been sent off again to be cut.
More to follow when I have it.
(Thanks go to Mike, Luke, Jack and Simon for your help advice and services)
Many of you may have seen my post RE: Laser Cutting and the Scaling up of 7mm Drawings, (which I see also helped another member) and this finally gave me a big kick up the backside to start one of the big projects I have wanted to do for a little while, and would hopefully be a big learning curve at the same time. It wasn’t what I was originally going to do Project Wise as my original plan was to design and build a FfR Funkey to go with the rest of my stock which is slowly increasing in size, but I found this too complex having only just started out with the software coupled with it being the first stuff I'd done in CAD in years!! So I went for Option 2 which wouldn't be as complex (however I'm not saying that now after designing it though!)
The plan was to build a Multi-Purpose Vehicle which can, as its name suggests, undertake many different roles depending on the Modules fitted to it. There was also a requirement to be able to extend the unit as required and also be able to work in multiple with other units.
So after a bit of discussion with another Forum Member regarding Laser Cutting, I began to draw up a plan in LibreCAD and after a lot of frustration and swearing at the computer along with some help and advice the plan soon came together, a few obvious mistakes were ironed out it was sent off to be cut.
The parts arrived promptly within a couple of days and the Prototype was soon together, however I found a few places where I had gone wrong (solebar tabs 3mm out, cab front tabs to small etc.) but it wasn’t anything that couldn’t be changed easily ready for the Mk2 Version.
So here are a few pictures to get you started.
After a weekend of tinkering and getting everything changed and adding extra bits the plans have been sent off again to be cut.
More to follow when I have it.
(Thanks go to Mike, Luke, Jack and Simon for your help advice and services)
Cheers Tom
- The Denying Dutchman
- Cleaner
- Posts: 85
- Joined: Thu Aug 08, 2013 10:27 am
- Location: Assen, the Netherlands
Re: Operation Multi Purpose
That seems to be a universal law in model building of any sort. I've got more projects in mind and on the shelf that I've got to reach an age of at least 150 to complete them all!Tom:87189 wrote:Right, so as you all probably know by now I’m good at thinking of projects and starting them, but I never seem to get around to finishing them! :lol:
As for the project in this thread: I have the feeling that a crane is involved else I have no clue what you're building.
Paul
Re: Operation Multi Purpose
I had thought about a crane module, but didn't know where to start design wise, or what was available, but I'm sure a bit of market research won't go amiss! If your still none-the-wiser then google 'Network Rail MPV's' then you'll soon know what I'm talking about/thinking along the lines ofThe Denying Dutchman:87193 wrote:As for the project in this thread: I have the feeling that a crane is involved else I have no clue what you're building.Tom:87189 wrote:Right, so as you all probably know by now I’m good at thinking of projects and starting them, but I never seem to get around to finishing them! :lol:
I put the first coat of paint on the Prototype/testbed earlier to see what it looks like, and I must say it looks great. I can't wait till the postman delivers the Mk2 Version!
Cheers Tom
- The Denying Dutchman
- Cleaner
- Posts: 85
- Joined: Thu Aug 08, 2013 10:27 am
- Location: Assen, the Netherlands
Hi All,
Now that the 2 week busy period is over and done with, it was time to get the MPV Mk2 Components out of the box again for a closer look and have a quick slot together to see what still requires work.
The overlays were cut out as well but require a little more work yet, along with a minor change to the sides.
So here is a mock up to give you an idea of how its looking at the moment: (Don't forget that there will be 2 of these back to back with a wagon in between too) This unit is fitted with a Ballast Module which still requires work also.
As said above there are a still a few changes that I want to make, one being those rear handrails, they are too chunky and will now be resized to 5mm thick, along with some alterations to the power bogie.
Now that the 2 week busy period is over and done with, it was time to get the MPV Mk2 Components out of the box again for a closer look and have a quick slot together to see what still requires work.
The overlays were cut out as well but require a little more work yet, along with a minor change to the sides.
So here is a mock up to give you an idea of how its looking at the moment: (Don't forget that there will be 2 of these back to back with a wagon in between too) This unit is fitted with a Ballast Module which still requires work also.
As said above there are a still a few changes that I want to make, one being those rear handrails, they are too chunky and will now be resized to 5mm thick, along with some alterations to the power bogie.
Cheers Tom
Hi All,
I suppose its time for another update;
So now that the minor problems have been sorted out I have started to glue together the components for the first unit. Here's some photos showing the construction and then a mock up of the two units together.
Floor and Solebars:
Front Buffer Beam:
Rear Buffer Beams and Handrail:
Cab Back:
Cab Sides:
2 Units together: Newest Variant at the Front with the Older unit at the back, but using the new handrail for a comparison.
Enjoy,
Tom
I suppose its time for another update;
So now that the minor problems have been sorted out I have started to glue together the components for the first unit. Here's some photos showing the construction and then a mock up of the two units together.
Floor and Solebars:
Front Buffer Beam:
Rear Buffer Beams and Handrail:
Cab Back:
Cab Sides:
2 Units together: Newest Variant at the Front with the Older unit at the back, but using the new handrail for a comparison.
Enjoy,
Tom
Cheers Tom
-
- Driver
- Posts: 1508
- Joined: Thu Jan 07, 2010 11:46 pm
- Location: LEICESTER
- Dr. Bond of the DVLR
- Retired Director
- Posts: 4485
- Joined: Tue Jun 09, 2009 9:43 pm
- Location: Suffolk
- Contact:
Hi All,
Thanks Methssniffer and Zach for your comments and the link!
Progress has been slow these last few days as work and other commitments have all got in the way.
Anyway, the postman has been delivering a stream of Parcels in the last couple of days, first of all the second unit arrived, then today the centre wagon and the modules also arrived.
Here's some more pictures:
The two units side by side:
Centre Wagon:
The whole train together, its just shy of being a metre long:
The new and improved ballast module, these are the main 3mm parts excluding the 1.5mm overlays.
The Water Tank Module 3mm pieces also excluding the 1.5mm overlays.
The Water Tank Module, I plan to fit some lights down the side as the real MPV's do, the electrics for this can be hidden in here as the tank will be removable.
Handrails:
Module feet to attach to the Units deck.
Some photos of the module fitted on the back of the unit.
Tom
Thanks Methssniffer and Zach for your comments and the link!
Progress has been slow these last few days as work and other commitments have all got in the way.
Anyway, the postman has been delivering a stream of Parcels in the last couple of days, first of all the second unit arrived, then today the centre wagon and the modules also arrived.
Here's some more pictures:
The two units side by side:
Centre Wagon:
The whole train together, its just shy of being a metre long:
The new and improved ballast module, these are the main 3mm parts excluding the 1.5mm overlays.
The Water Tank Module 3mm pieces also excluding the 1.5mm overlays.
The Water Tank Module, I plan to fit some lights down the side as the real MPV's do, the electrics for this can be hidden in here as the tank will be removable.
Handrails:
Module feet to attach to the Units deck.
Some photos of the module fitted on the back of the unit.
Tom
Cheers Tom
- Lner fan Sam
- Fireman
- Posts: 491
- Joined: Sun Nov 25, 2012 7:57 pm
- Location: Sunderland, north east of England
-
- Driver
- Posts: 1508
- Joined: Thu Jan 07, 2010 11:46 pm
- Location: LEICESTER
Hi All!
Thanks L and B mad and Methssniffer - I had seen that but didn't really catch my eye
Here's a bit more progress from over the weekend -sorry for the quality of the photos, I grabbed them quickly before the light went too much!
As you will see I managed to fit the light clusters to Unit 1 along with the headlight surround to help add a bit of depth and detail to the front of the unit. I did find one problem whilst fitting them though and that is as follows: The coupling is currently in line with the bottom of the light clusters so this will be packed out to leave enough room for it when coupling up with other units, should be a quick fix
So as you can see tonight's job will be to remove that excess filler from around the light clusters and then give them a couple of coats of primer in readiness for some yellow paint tomorrow!
The rear deck on which the modules sit also got a lick of black paint today with the locating peg tops getting a quick coat of white
The Water Tank Module as it was at the close of play fixed on the back of Unit 1, with the handrail posed in front.
Enjoy
Thanks L and B mad and Methssniffer - I had seen that but didn't really catch my eye
Here's a bit more progress from over the weekend -sorry for the quality of the photos, I grabbed them quickly before the light went too much!
As you will see I managed to fit the light clusters to Unit 1 along with the headlight surround to help add a bit of depth and detail to the front of the unit. I did find one problem whilst fitting them though and that is as follows: The coupling is currently in line with the bottom of the light clusters so this will be packed out to leave enough room for it when coupling up with other units, should be a quick fix
So as you can see tonight's job will be to remove that excess filler from around the light clusters and then give them a couple of coats of primer in readiness for some yellow paint tomorrow!
The rear deck on which the modules sit also got a lick of black paint today with the locating peg tops getting a quick coat of white
The Water Tank Module as it was at the close of play fixed on the back of Unit 1, with the handrail posed in front.
Enjoy
Cheers Tom
That all looks great Tom, I was wondering how all those little bits fitted together.
Mike
Wood Valley Works
http://www.woodvalleyworks.co.uk
Wood Valley Light Railway
http://www.wvlr.co.uk
Wood Valley Works
http://www.woodvalleyworks.co.uk
Wood Valley Light Railway
http://www.wvlr.co.uk
Thanks Mike, it was a mare thinking of an easy way of doing those! turns out one area was about a 1mm too big but that's hidden and was easy to remove so wasn't a problem. I've used the filler to cover up the tabs. I will give it a coat of yellow later, and see what it looks like. :DWVLR:89872 wrote:That all looks great Tom, I was wondering how all those little bits fitted together.
Cheers Tom
Who is online
Users browsing this forum: No registered users and 4 guests